Progress: Meiko electric manufatory phase 3 to 18/04/2019

By April 18, 2019, the project: MEIKO Electronics Vietnam Factory Phase 3 reached the progress at the request of the Owner.

Specifically:

+) Factory No. 3:

– Complete 100% of the structure

– Completion of 95% of finishing: clean room panel installation; erection of purlins, wall construction, installation of structural steel for the 1st floor equipment, chiller pipe support, installation of fire-fighting water supply pipes, air-conditioning pipes, sanitary equipment, tiled floor 4 and toilet born …

+) Extended ESD house:

– Complete 100% of the structure

– Completion of 99% of finished parts: construction of walls, plastering, painting inside and outside the house, epoxy coating on floors …

– Construction of 99% of piperack system

+) EMS house:

– Complete 100% of the structure

– Completing 90% of the finished part: building walls, outdoor plastering, painting inside and outside the house, installing clean room panel, erecting wall purlins, correcting walls, installing water supply systems, sanitary tiling …

Some pictures of the construction site

 