Project progress: Bach Viet Apartment Complex – Bac Giang to 16/04/2019

By April 16, 2019 project: Bach Viet Areca Garden Apartment – Bac Giang reached the progress as required by the Owner.

Specifically:

1. Finished surface primer.
2. Completed 2 underground tanks outside the house.
3. Completed construction of tiled floors.
4. All jobs have reached the set progress.
5. It is expected that 30/5/19 will be tested intermittently.