Dabaco Ly Thai To Bac Ninh project progress 12/2020

 

 

No.

Content of the work should be done by November 30, 2020

Reality

Evaluate according to progress

I

Construction and installation contractor-Licogi12 Joint Stock Company

first

Construction of wall, wall to the roof

No construction, complete technical box.

Delay in progress according to progress requirements until September 3, 2020, construction and completion of construction to the roof floor (problematic)

2

Construction of plastering from the basement to the roof.

Basement area has not been plastered yet. Completion from 1st floor to rooftop.

Delayed according to progress requirements until November 21, 2020, construction completed (problems with the ground)

 

3

Execution of plastering outside from 01 to the roof

 

98%

 

4

Waterproofing toilets, balconies, loggias of apartments from 4th floor to 10th floor

The waterproofing of floors 04 to 9 has been implemented

Delayed according to progress requirements until 11/26/2020 (lack of manpower)

5

Grounding in apartments from 4th floor to 12th floor

Qualified

According to the progress on January 14, 2020, screed will be completed to the 15th floor.

6

Wall tiling in the house from 5th to 10th floor

Deployed tiles from floor 05 to floor 08

There is a risk of delaying progress according to progress requirements until December 10, 2020, completing tiling to the 10th floor (lack of manpower, space)

7

According to progress requirements 6/1/2020, complete plaster ceiling to the 10th floor

Construction of plasterboard ceiling, finishing floor 05,06,07, floor 09 (07 units), floor 10 (12 units), shot plate on the 05th floor.

Qualified

8

Construction of jealous tube shot, electric ceiling, flat wire, corridor 

Ceiling jealous tube shot (Basement-11th floor), wall jealous tube (basement-15th floor), corridor is not friendly

Delayed progress (lack of manpower + materials)

9

Construction of water supply for apartments

Construction of floors 01 to 15

Delayed according to the progress request is September 13, 2020 completed.

ten

Deploying the construction of apartment wire drawing from September 1, 2020

Completed construction of the 05,06,07,09,10 floor

Delayed according to the progress requirement is 11/7/2020, completed from 4th floor to 10th floor.

11

Construction of collection pipe system, pump pipe to the tank

No construction yet

17 days behind schedule as required by September 13, 2020 to finish to the 15th floor

II

Fire Protection Contractor - Hanoi Fire Protection Construction Joint Stock Company

II.1

Fire System

 

 

first

Installation of vertical shaft, dry throat

Construction from tunnel to roof (80%).

 

 

 

Slow progress

2

Construction of Prinkler shaft from tunnel to roof (tunnel to roof).

Construction from tunnel to roof (70%).

3

Construction of ring circuit and branch arms.

Has implemented the construction of basement to the roof (80%).

4

Construction of equipment

Undeveloped

II.2

Fire alarm system

 

 

first

Installation of jing pipes, wire ropes

Construction of floors 4-15

Qualified

2

Pull out the fire signal wire

Construction of floors 4-15

Qualified

4

Installation of fire alarms

10%

Slow progress

II.3

Construction of gas fire extinguishing system FM

 

 

first

Construction of fire alarm system

No construction yet

 

2

Construction of fire alarm system

No construction yet

 

III

Contractor for constructing ventilation system, pipeline waiting for air conditioning, constructing light power system - Tan Tien Technical Service Co., Ltd.

first

 Construction of ventilation system in the basement

Undeveloped

 

Slow progress

2

Construction of smoke extraction system in corridors, commercial centers

Completed from 4th floor to 15th floor. Commercial smoke is available

Guaranteed progress

3

Installation of condenser drainage pipes, copper pipes and fittings.

Deployed floors 4 to 15

Qualified

4

Construction of light cable trough system

Deployed floors 4 to 15

Qualified

IV

Lightning protection contractor - ETI Technology Joint Stock Company

first

Construction of lightning protection system

Accomplished

Qualified

V

 Elevator and escalator construction contractor-Mitsubishi Elevator Company Limited

   

first

Complete the installation of stairs P1, P2, P3, P4, P5, P6.

Accomplished

 

 

Qualified

2

Completion of escalator installation

Accomplished

3

Completed construction and installation of the elevator

Slow

Delayed due to the lack of premises

BECAUSE

TBA substation construction contractor : Tan Nhat Minh Company Limited

first

Completion construction placed underground HDPE pipes from the connection point to the medium voltage cabinet.

Completed

 

Qualified

2

Transformer, medium voltage cabinets RMU gathered on the site

 

Qualified

VII

Construction contractor for swimming pool system:  An Thai filtration equipment technology joint stock company

first

Start receiving construction site on 11/27/2020

 

 

VIII

Light power system contractor:  Tuong Mai Trading and Service Co., Ltd (Telephone cable, internet cable)

first

- Installation of wall-mounted jig pipes on floors 4 to 15

Completed

Qualified

 

Some pictures at the work

 