No. |
Content of the work should be done by November 30, 2020 |
Reality |
Evaluate according to progress |
|
I |
Construction and installation contractor-Licogi12 Joint Stock Company |
|||
first |
Construction of wall, wall to the roof |
No construction, complete technical box. |
Delay in progress according to progress requirements until September 3, 2020, construction and completion of construction to the roof floor (problematic) |
|
2 |
Construction of plastering from the basement to the roof. |
Basement area has not been plastered yet. Completion from 1st floor to rooftop. |
Delayed according to progress requirements until November 21, 2020, construction completed (problems with the ground) |
|
3 |
Execution of plastering outside from 01 to the roof |
98% |
|
|
4 |
Waterproofing toilets, balconies, loggias of apartments from 4th floor to 10th floor |
The waterproofing of floors 04 to 9 has been implemented |
Delayed according to progress requirements until 11/26/2020 (lack of manpower) |
|
5 |
Grounding in apartments from 4th floor to 12th floor |
Qualified |
According to the progress on January 14, 2020, screed will be completed to the 15th floor. |
|
6 |
Wall tiling in the house from 5th to 10th floor |
Deployed tiles from floor 05 to floor 08 |
There is a risk of delaying progress according to progress requirements until December 10, 2020, completing tiling to the 10th floor (lack of manpower, space) |
|
7 |
According to progress requirements 6/1/2020, complete plaster ceiling to the 10th floor |
Construction of plasterboard ceiling, finishing floor 05,06,07, floor 09 (07 units), floor 10 (12 units), shot plate on the 05th floor. |
Qualified |
|
8 |
Construction of jealous tube shot, electric ceiling, flat wire, corridor |
Ceiling jealous tube shot (Basement-11th floor), wall jealous tube (basement-15th floor), corridor is not friendly |
Delayed progress (lack of manpower + materials) |
|
9 |
Construction of water supply for apartments |
Construction of floors 01 to 15 |
Delayed according to the progress request is September 13, 2020 completed. |
|
ten |
Deploying the construction of apartment wire drawing from September 1, 2020 |
Completed construction of the 05,06,07,09,10 floor |
Delayed according to the progress requirement is 11/7/2020, completed from 4th floor to 10th floor. |
|
11 |
Construction of collection pipe system, pump pipe to the tank |
No construction yet |
17 days behind schedule as required by September 13, 2020 to finish to the 15th floor |
|
II |
Fire Protection Contractor - Hanoi Fire Protection Construction Joint Stock Company |
|||
II.1 |
Fire System |
|
|
|
first |
Installation of vertical shaft, dry throat |
Construction from tunnel to roof (80%). |
Slow progress |
|
2 |
Construction of Prinkler shaft from tunnel to roof (tunnel to roof). |
Construction from tunnel to roof (70%). |
||
3 |
Construction of ring circuit and branch arms. |
Has implemented the construction of basement to the roof (80%). |
||
4 |
Construction of equipment |
Undeveloped |
||
II.2 |
Fire alarm system |
|
|
|
first |
Installation of jing pipes, wire ropes |
Construction of floors 4-15 |
Qualified |
|
2 |
Pull out the fire signal wire |
Construction of floors 4-15 |
Qualified |
|
4 |
Installation of fire alarms |
10% |
Slow progress |
|
II.3 |
Construction of gas fire extinguishing system FM |
|
|
|
first |
Construction of fire alarm system |
No construction yet |
|
|
2 |
Construction of fire alarm system |
No construction yet |
|
|
III |
Contractor for constructing ventilation system, pipeline waiting for air conditioning, constructing light power system - Tan Tien Technical Service Co., Ltd. |
|||
first |
Construction of ventilation system in the basement |
Undeveloped |
Slow progress |
|
2 |
Construction of smoke extraction system in corridors, commercial centers |
Completed from 4th floor to 15th floor. Commercial smoke is available |
Guaranteed progress |
|
3 |
Installation of condenser drainage pipes, copper pipes and fittings. |
Deployed floors 4 to 15 |
Qualified |
|
4 |
Construction of light cable trough system |
Deployed floors 4 to 15 |
Qualified |
|
IV |
Lightning protection contractor - ETI Technology Joint Stock Company |
|||
first |
Construction of lightning protection system |
Accomplished |
Qualified |
|
V |
Elevator and escalator construction contractor-Mitsubishi Elevator Company Limited
|
|||
first |
Complete the installation of stairs P1, P2, P3, P4, P5, P6. |
Accomplished |
Qualified |
|
2 |
Completion of escalator installation |
Accomplished |
||
3 |
Completed construction and installation of the elevator |
Slow |
Delayed due to the lack of premises |
|
BECAUSE |
TBA substation construction contractor : Tan Nhat Minh Company Limited |
|||
first |
Completion construction placed underground HDPE pipes from the connection point to the medium voltage cabinet. |
Completed |
Qualified |
|
2 |
Transformer, medium voltage cabinets RMU gathered on the site |
|
Qualified |
|
VII |
Construction contractor for swimming pool system: An Thai filtration equipment technology joint stock company |
|||
first |
Start receiving construction site on 11/27/2020 |
|
|
|
VIII |
Light power system contractor: Tuong Mai Trading and Service Co., Ltd (Telephone cable, internet cable) |
|||
first |
- Installation of wall-mounted jig pipes on floors 4 to 15 |
Completed |
Qualified |
Some pictures at the work