Progress of construction project of Hoang Huy So Dau mixed-use building, Hai Phong in December 2021

On November 25, 2021, the construction progress of the project "Mixed building under Hoang Huy - So Dau project" until the date of meeting the requirements of the investor with the details below:

  1. Construction work.
  • Finished construction of floor girder concrete floor 24
  • Construction of walls in the apartment to the 17th floor.
  • Placing in the apartment until T12.
  • Construction of plaster ceiling, waterproofing, floor rolling in the apartment up to the 8th floor.
  • Construction of electricity, water, fire protection until T14
  1. About construction progress:
  • The progress of the construction of the raw and finished parts is in comparison with the progress approved by the Investor.
  • The progress of the ME part is about 7 days behind the schedule approved by the Investor

Some pictures at the project

 

 

 