Progress of Renovations and upgrade The Lang Thuong primary school

Progress of Renovation and upgrade the Lang Thuong primary school in July, 2020 as details:

I. Construction implement of School Management building

  + Complete the tiling construction of the 2,3,4 floor;

  + Finish the roof construction;

  + Completing the finishing work.

II. Construction implement of lecture hall     

  + Completed the work of painting with 01 layer solid paint to reach 80% volumn of new lecture hall.

  + Completed the tiling work for stairs of new lecture hall;

  + Implementing the ceiling construction for the 2,3,4 floor to reach 90% volumn of new lecture hall.

  + Conpleted the tilling work for the restroom of the new lecture hall;

  + Implementing the roofing tile work for the new lecture hall.

  + Installing the window for the new lecture hall,

  + Outpainting for the new lecture hall

  + Cleaning

III. Constructioning the underground water tank for fire protection

  + Cleaning to prepare for concrete floating of underground water tank for Fire protection.

  - Bid package No 13: demolition of old building, prepare the work ground for testing pile pressing. Contract No 30/2019/HĐ-XDCB/HP issued on 21/11/2019

  + Demolition of old building   

   + Cleaning    

The work of labor safety and sanitation is strictly implemented in accordance with current laws, decrees and circulars.