On August 1, 2019, General Director Tran Viet Cuong visited and had a meeting with the supervision consultant team at the construction site. The project meets the requirements and schedule of the Investor. As follows:
Range 1:
-Color of finishing inside and outside walls;
- Installation of aluminum and glass frames, wooden doors
-Installing handrail in and out of the house;
-Pipe, brick, wooden floor;
-Installing air-conditioning equipment;
Range 2 + 3
-Dust, primer inside and outside the house;
-Installing aluminum and glass door frames;
-Installing handrail in and out of the house;
-Pipe, brick, wooden floor;
Execution of M.E
Range 9 + 10 + 11:
-Dust, primer inside and outside the house;
Execution of M.E