Progress of the Tokyo Medical University Hospital project in March 2021

Project progress to the end of March 2021:

- Construction of completed structural components of the main building

- Construction of infrastructure around the house: 70%.

- Construction completed in the main building block:

+ 1st floor: basic construction complete plaster wall, rough construction, and erection of electromechanical system.

+ Level 2: construction of crude construction, drywall: 70% of the volume of floors, construction of electromechanical systems of floors: 60%.

+ 3rd floor: construction of raw construction, drywall: 50% volume of floors 

+ Roof floor: complete construction of elevator tum structure.