The Supervisory Board of the Housing project for sale to Hanoi police officers and soldiers and other subjects reported the construction progress in May 2022 as follows:
- Exterior plastering of 15-storey building with the volume of 90%
- Construction of motorcycle ramp railings with volume of 90%
- Plastering in apartments on floors 5,6,7,10 achieved 30% volume
- Plastering walls of floors 5,6,7,9,11,12,13 with volume of 50%
- Construction of ME system on floors 5,6,7,8,9,10,11,12,13 with volume of 5%
- Construction of underground water supply pipes for garbage rooms on floors 5,6,7,8,9,10,11,12,13,14,15 with 95% volume - Construction of corridor fire alarm system, fire fighting system for floors 15 - 20 reached 70% volume