Project progress of PAPVN factory production expansion November 1, 2023

       In November 2023, CONINCO 3C Joint Stock Company updated the project. "Expanding production of PAPVN 1 factory" at location "Lot B6, Thang Long Industrial Park, Dong Anh, Hanoi. The project is being implemented according to the schedule set by the investor. Details are in the following table:

Project scale: 5,389 m2 

Construction progress: 

- Piling work: reached 100%

- Excavation work: reached 100%

- Construction of formwork, reinforcement, concrete for foundation bracing: reached 100%

- Land filling and leveling work: reached 100%

- Compaction, sand compaction, base spreading work: reached 100%

- Erection of steel column frames and steel trusses: reached 100%

- Purlin erection work: reached 100%

- Construction of corrugated iron roofs, corrugated iron walls, main house wall construction: 100%

- M&E construction + fire protection: 70%

- Construction of new garage area: not yet constructed

- Construction of road connecting old factory to new factory: reached 20%

 

 

 

 