Coninco 3C Supervision consultant team of "Houses for sale to Hanoi police officers and soldiers and others" project participated in the Groundbreaking ceremony of the package "Constructing foundation, body, and finishing outside 9NO"
- Starting date: 3/6/2020
- The scale of bidding package: 28 adjacent houses, height: 5 floors, construction area of 2600m2
- Construction progress: 210 days
Current project progress:
+ Completion of mass pile pressing has accumulated 474/474 piles
+ Checking the payment documents for phase 1 of a package of construction of pressing piles
+ Implementing the preparation for the package of executing the foundation and the body.
Some pictures at the ceremony and the construction site