Main house block
- Construction of concrete on the first floor beam cote 0.00: 100%
- Construction of concrete on the first floor elevator: 100%
- Construction of concrete on the first floor: 100%.
- Construction and erection of scaffolding on the 2nd floor: 15%
Mechanical and Electrical Part
- Waiting system for drainage pipes and electricity on the 1st floor: 100% (zone A + B)
-Testing the pressure waiting for the fire pipe on the first floor: 100% (zone A + B)
- Fabrication of the ventilation pipes Fire pipeline at the contractor warehouse.
- Put HDPE pipes waiting for garage lighting system.
Infrastructure outside the house
- Construction of pits for MEP: 100%
- Road side drainage ditch XC1: 100%.