Dabaco Ly Thai To Bac Ninh project progress

Dabaco Ly Thai To Bac Ninh project progress

The progress of Dabaco Bac Ninh project in October 2020 achieved the workload as follows:

 

Construction of finishing the structure to the 15th floor

Construction of walls from the first floor to the roof floor reaches 95%

 

Plastering work in buildings from floor 1 to floor 11 reaches 98%

 

Plastering from floors 03 to floor 01 reaches 98%

 

Plastering for buildings from 10th to 4th floor reaches 80%

 

Plastering works from outside to the eleventh floor reaches 20%

Construction of waterproofing toilets, balconies, loggias on the 5th floor reaches 80%

 

Construction of screed on floors 04 to 07 reaches 90%

Construction of electricity and water to the 15th floor reaches 30%

Construction of ventilation, pipeline waiting for air conditioning to the 15th floor reaches 95%

 

 

Fire protection construction to the 15th floor reaches 85%

Construction of lightning protection system reaches 98%

 