The progress of Dabaco Bac Ninh project in October 2020 achieved the workload as follows:
Construction of finishing the structure to the 15th floor
Construction of walls from the first floor to the roof floor reaches 95%
Plastering work in buildings from floor 1 to floor 11 reaches 98%
Plastering from floors 03 to floor 01 reaches 98%
Plastering for buildings from 10th to 4th floor reaches 80%
Plastering works from outside to the eleventh floor reaches 20%
Construction of waterproofing toilets, balconies, loggias on the 5th floor reaches 80%
Construction of screed on floors 04 to 07 reaches 90%
Construction of electricity and water to the 15th floor reaches 30%
Construction of ventilation, pipeline waiting for air conditioning to the 15th floor reaches 95%
Fire protection construction to the 15th floor reaches 85%
Construction of lightning protection system reaches 98%