Dabaco Ly Thai To project progress Bac Ninh 5/2021

Dabaco Bac Ninh project progress in May 2021 reached the following workload

Exterior painting construction on floors 1-4 (commercial and service area) (primer has been applied):  50%

Construction of drop ceiling gypsum board 1-3 frequency TMDV:  30%

Construction and installation of electrical equipment in basements, floors 1, 2, 3 and attic:  20%

Construction and installation of power distribution cabinets on floors, function room areas:  50%

Construction and installation of sanitary equipment for the base block:  20%

Construction of vertical shaft for water supply stainless steel pipe:  40%

 

Some pictures at the project 

 

 

 

Complete construction and connection of roof fans:  75%

Install a toilet exhaust fan in the apartment:  40%