Progress of ATR Hai Duong Factory Project - December 2024

The ATR Hai Duong Factory Project is a key project located in the An Phat 1 Industrial Park, with the aim of constructing a modern industrial production facility that meets international standards in technology and environmental protection. The factory broke ground in March 2024 and is currently implementing various construction items. The progress of some key items is as follows:

  • Factory construction: the main structure is 100% complete, floor structure at +0.00 level is 98% complete.
  • Multi-purpose building construction: structural work is complete, finishing progress exceeds 60%.
  • Construction of the car park and auxiliary buildings: structural work is complete, finishing work is underway.
    The ATR Hai Duong Factory Project is progressing on schedule, ensuring labor safety and construction quality requirements. With close coordination between the investor, CONINCO 3C supervision consultant, and contractors, the project will soon be completed and put into operation, contributing to economic development and creating more job opportunities for the local community. Below are some updated images from the project: