Sending...
  • Vietnamese English

Lượt truy cập hôm nay: 620

Lượt truy cập hôm qua: 923

Lượt truy cập tháng: 329524

Tổng truy cập: 3323006

  • Vietnamese English

Progress of Dabaco apartment and townhouse projects, Ly Thai To street, Bac Ninh city on August 12, 2019

On August 12, 2019, the project of Dabaco Apartment, Shophouse, Ly Thai To Street, Bac Ninh City has achieved the following progress:

1. Extraction of 100% pile
2. Digging the basement land reaches 75%
3. Constructing concrete with concrete, bracing foundation reaches 60%
4. Leveling and placing concrete with 30% of foundation
5. Ground waterproofing reaches 25%
6. Installation of reinforcement in basement wall walls reaches 25%
7. Fabrication of reinforced basement at 10%

Some pictures of the construction site

 

 

Project

Other news