Project progress: Golden Land Building, Service, and Housing Building - 275 Nguyen Trai, Thanh Xuan, Hanoi reached the progress as required by the Investor.

1- The roof of the project was kept on May 14, 2019 (exceeding the project schedule)

2-Raw construction to 33rd floor (ensure progress)

3- Plaster to 24th floor (ensure progress)

4- The 21st floor

5- Aluminum glass is implementing shopping mall

6- Electromechanical system to floor 26

Some pictures of the construction site

 