On August 5, 2019, the progress of ICID Project Le Trong Tan is as follows
About construction:
- Swimming pool cladding: 5%
- Swimming pool cladding: 100%;
- Slices of 0.00: 100%
- Plastering outside domestic water tanks: 100%
- Construction of basement wind wall 2: 100%
About aluminum and glass:
- Body: Go glue, window accessories, lot 1: back to the 5th floor (1/26 floor); zone 2: remaining floors 6-9 (4/26 floors);
- Gathering materials of podium floors 1,2,3:
- Frame 150/321 sets;
- Glass 80%;
About Wooden floors, wooden doors
- All rooms: Zone1 and 2: the fifth floor (1/26 floor);
- Track hoist: Zone 1: remaining floors 5-11, and floor 16 (8/26 floors).
Some photos at the construction