The supervision consultant team of project "Houses for sale to Hanoi police officers and soldiers and other subjects" reports the construction progress of November 2020 as follows:
- Package TVGS for construction of house 9NO
+ Ongoing construction of exterior plastering for 19/28 apartments
+ Deploy the construction of the raw body 22/28 units (19 completed units)
+ Construction of waterproofing for 10/28 apartments
+ Completion of the construction of the excavation and embankment of the remaining 2 sections to base B
+ The contractors for the installation of doors and termites are completing the preparation work, expected to be deployed in December