Progress of the project to expand production of PAPVN 1 factory at location "Lot B6, Thang Long Industrial Park, Dong Anh, Hanoi. Investor ''Panasonic Vietnam Co., Ltd.'' has almost completed and achieved quality and progress of the Investor in December 2023. Specifically as follows:
Project scale: 5,389 m2 including:
- Factory expansion.
- Other related items.
Construction progress:
- Piling work: reached 100%
- Excavation work: reached 100%
- Construction of formwork, reinforcement, concrete for foundation bracing: reached 100%
- Land filling and leveling work: reached 100%
- Compaction, sand compaction, base spreading work: reached 100%
- Erection of steel column frames and steel trusses: reached 100%
- Purlin erection work: reached 100%
- Construction of corrugated iron roofs, corrugated iron walls, main house wall construction: 100%
- M&E construction + fire protection: 100%
- Construction of new garage area: 100%
- Construction of road connecting old factory to new factory: reached 100%
- Construction of infrastructure outside the house: 90%