On January 6, 2021, Park Kiara - Park city high-end apartment project phase 3B achieved the following progress:
Basement block, basement: Complete 90% of reinforced concrete structures
Tower A: Construction of formwork, rebar of the 6th floor floor beam reaches 90%
Tower B: Construction of formwork, rebar of the 6th floor floor beam reaches 40%
Some pictures at the site