As of July 26, 2019, the project "Residential high-rise apartment building No16; No15" is progressing as required by the investor.
Photos and actual evaluation of project site progress. "Residential high-rise apartment building No16, No15". Investor "Hanoi Construction Joint Stock Company No. 3" No16 Construction includes 5 towers No16.1, No16.2, N016. 3, No16.4,5, Building No15 consists of 4 towers No15.1, No15.2, N015.3 and No15.4 The height of the floor consists of 15 floating floors and 01 basement. Basement floor B1 and landscape zone surrounds the buildings.
As follows:
Tower No16.1; No16.3 was built in June
Tower No16.2, No16.4.5 July 17, 2019, departs the roof.
Tower No15.3; N015.4; took the roof in June
Tower No15.1; N015.2; July 17, 2019, the departure of the roof.
Construction of the tunnel floor has been completed. Reach 100%.