Project progress of Junior Youth Theater II in December 2021

On December 1, 2021, the progress of the project of Tuoi Tre Theater II, reached the schedule required by the investor, specifically as follows:

-  Construction of the 3rd floor (axis 7-13/CH)  Installing reinforcement, formwork and pouring concrete at 100%

 Construction of the 4th floor (axis 7-10/CH) :  Installing reinforcement, formwork and pouring concrete at 100%

-  Construction of the 5th floor (axis 7-10/CH):  Installing reinforcement, formwork and pouring concrete at 100%

-  Construction of domestic water tanks and fire protection:  Construction of the rough part and waterproofing of the tank walls reached 100%

-  Construction of stand 1 (axis 2-8/BE):  Installing reinforcement, formwork and pouring concrete at 100%

-  Outside spear , anti-dust net (safety):  Construction of outdoor catholic work up to the 5th floor reaches 90%

-  Building walls in the basement:  Reach 30%