On June 2, 2021, the Park Kiara - Park city luxury apartment project phase 3B has achieved the following progress:
1. Construction of body structure:
- Tower A: Completed concrete pouring of floor beams on the 21st floor.
- Tower B: Construction of columns, walls and beams on floor 20
2. MEP work:
- Floor sound pipe system:
+ Tower A: to the 21st floor.
+ Tower B: to the 19th floor
- Complete:
+ Tower A to the 10th floor, the drainage shaft to the 14th floor.
+ Tower B to 9th floor, drainage shaft to 14th floor.
3. Finishing work:
- Tower A:
+ Complete the model apartment on the 5th floor.
Construction: 15th floor.
+ Inner plaster: 9th floor Tầng
+ Plastering: 11th floor to 5th floor
+ Rolling platform: 8th floor
+ Waterproofing: 7th floor
+ Paint: 9th floor.
- Tower B:
Construction: 13th floor.
+ Inner plaster: 7th floor.
+ Rolling platform: 5th floor
+ Waterproofing: 6th floor
+ Paint: 6th floor.
4. Covering works: 95%