Sending...
  • Vietnamese English

Lượt truy cập hôm nay: 340

Lượt truy cập hôm qua: 1034

Lượt truy cập tháng: 172218

Tổng truy cập: 3362685

  • Vietnamese English

Project progress Tokyo Medical University Hospital in June 2021

Project progress Tokyo Medical University Hospital in June 2021 has achieved the following workload:

Main building block: 

+ Completed construction of 80% of the volume of the apartment. (including works: paving, plaster ceiling construction, plaster wall...)

+ Construction of pipeline system, ME system route is basically completed

+ Construction and installation of indoor equipment 60% of the total volume of the building.

Infrastructure and ancillary works:

+ Implemented the basic construction of the internal road system around the main building, planting grass and trees around the building.

+ The security house, the house has basically completed the work (tiling, painting the house ..)

Some pictures at the construction site 

 

 

 

 

 

 

 

Project

Other news