On 20/7/2020, the project of Condominium and commercial shophouse DaBaCo – Bac Ninh is on the progress as details:
- Complete the concreting of the beam, floor, and rooftop reaches 100%. The Topping out ceremony is held on 28/6/2020
- Construction wall progress from the first to the eighth floor reaches 98%
- Construction wall progress the ninth floor reaches 50%
- Plastering progress the first and the second floor reaches 80%, the third floor reaches 50%
- General construction progress the sample on the fifth floor reaches 60%
- M&E construction progress from the basement to the third floor and from the seventh to twelfth floor reaches 10%, the forth reaches 30% and the fifth reaches 60%
- Thi công điều hòa thông gió tầng 4 đạt 40%, tầng 5 đạt 70%,
Construction the air conditional progress in the forth reaches 40%, the fifth reaches 70%
- PCCC từ tầng 1 đến tầng 4 đạt 50%, tầng 5 đạt 70%