Construction progress of Goldenland 5 - Renovating old and dangerous apartments in Hai Phong city HH1-HH2 June 2021 is as follows:
BUILDING HH1
Structure Construction of floor beams to the 27th floor is 100% complete
Construction of apartment walls up to the 16th floor reached 50%
The tiling work of 3rd and 4th floor reached 65%
The work of painting the outside walls of the chopping block 1 to 3-9 reaches 70%
Prime the exterior wall of the chopping board 1 floors 3-9 reaching 50%
Waterproofing of WC, lot of floors 3-10 reached 50%
LD gypsum ceiling work, bare skeleton of the apartment on the 3-5 floor
Construction of electric cable trays, light electricity, water supply in floor corridors, fire fighting system in corridors of floors 3-9 completed 50%
BUILDING HH2
Building walls of apartments on floors 14-16 reached 50%
Plastering walls in apartments on floors 3-9 reached 95%
Flooring of 3rd and 4th floor apartments reaches 65%
Exterior wall of the chopping block 1 floors 3-9 reached 70%
Prime the outside wall of the cutting board 1 floors 3-9 reaching 50%
Construction of fire fighting system 3-9 floors reached 95%
Construction of fire fighting system 3-9 floors reached 65%