Sending...
  • Vietnamese English

Lượt truy cập hôm nay: 642

Lượt truy cập hôm qua: 923

Lượt truy cập tháng: 329546

Tổng truy cập: 3323028

  • Vietnamese English

Construction project progress of Berriver Long Bien structure in June,2021

In June 2021, the construction project progress of Berriver Long Bien works meets the requirements of the investor, details are as follows:

Court N02:

- Plastering in floors 1 to 20

- Installing frames and glass windows from 3rd floor to 20th floor, reaching 90%

- Installing loggia doors from 3rd to 10th floor, reaching 20%

- Rolling of apartment floors from 3rd floor to 6th floor reaches 90%

- Grade 1 baits from 3rd to 8th floor reach 90%

- Plastering toilets on the 3rd and 4th floors reached 80%

- Waterproofing of toilets and loggias from 3rd to 6th floors reaches 60%

- Conduit and wire the electrical system at 90%

- Water supply system for floors 3-20 reaches 90%

- Drainage system for floors 3-30 reaches 70%

- Installation of fire hoses in corridors of floors 2 - 20 reached 80%

House N04:

- Grade 1, 2nd-5th, get 20%

- Rolling the 4th floor reaches 5%

- Installation of aluminum window frames from 2nd to 10th floor reaches 45%

- Installing conduit on the 2-20th floor, the technical floor reaches 20%

- Installation of fire hoses in the corridor area from the 2nd to the 18th floor reaches 80%

House N05:

- Building exit shafts for floors 2-4 reach 80%

- Installation of fire hoses for the 3rd floor corridor sample reached 30%

Some pictures at the construction site 

 

 

 

 

Project

Other news