In June 2021, the construction project progress of Berriver Long Bien works meets the requirements of the investor, details are as follows:
Court N02:
- Plastering in floors 1 to 20
- Installing frames and glass windows from 3rd floor to 20th floor, reaching 90%
- Installing loggia doors from 3rd to 10th floor, reaching 20%
- Rolling of apartment floors from 3rd floor to 6th floor reaches 90%
- Grade 1 baits from 3rd to 8th floor reach 90%
- Plastering toilets on the 3rd and 4th floors reached 80%
- Waterproofing of toilets and loggias from 3rd to 6th floors reaches 60%
- Conduit and wire the electrical system at 90%
- Water supply system for floors 3-20 reaches 90%
- Drainage system for floors 3-30 reaches 70%
- Installation of fire hoses in corridors of floors 2 - 20 reached 80%
House N04:
- Grade 1, 2nd-5th, get 20%
- Rolling the 4th floor reaches 5%
- Installation of aluminum window frames from 2nd to 10th floor reaches 45%
- Installing conduit on the 2-20th floor, the technical floor reaches 20%
- Installation of fire hoses in the corridor area from the 2nd to the 18th floor reaches 80%
House N05:
- Building exit shafts for floors 2-4 reach 80%
- Installation of fire hoses for the 3rd floor corridor sample reached 30%
Some pictures at the construction site