During the March inspection, the General Director of CONINCO 3C visited and worked with the Commerce Hai Phong project staff. Officers are always compliant and disciplined and ensure the best quality is reported. Some project progress information is as follows:
1. Construction of Semi-floor basement B1, basement B2, Floor 1 (100%)
2. Construction of basement foundation B3 at -11.15m (55%)
3. Construction of opening lock (10%)
4. Construction of pit station Tower A, B, C (100%) On schedule
5. Construction of tower petals A, B, C (100%) On schedule
6. Construction of single foundation station (including basement B3) Tower A, B, C Under construction