On 08/10/2018, the project of Meiko Electric manufactory construction phase 3 meet the requestment.
Details:
+) Number 3 manufactory:
– Completed 95% of the structure
– Completed 35% finishing: Cleanroom panel installation; building wall purlins, building walls, installing structural steel support equipment floor 1, supporting chiller pipes, water supply pipes, fire fighting, air conditioning pipes …
+) Expanded EMS House:
– Completed 95% of the structure
– Complete 50% of finishing: building wall, plaster …
– Execute 80% piperack system
+) Expanded EMS House:
– Completion of 70% of the structure: 3rd floor is 50%, 4th floor is 30%