Progress: Meiko electric manufatory phase 3

On 08/10/2018, the project of Meiko Electric manufactory construction phase 3 meet the requestment.

Details:

+) Number 3 manufactory: 

– Completed 95% of the structure

– Completed 35% finishing: Cleanroom panel installation; building wall purlins, building walls, installing structural steel support equipment floor 1, supporting chiller pipes, water supply pipes, fire fighting, air conditioning pipes …

+) Expanded EMS House:

– Completed 95% of the structure

– Complete 50% of finishing: building wall, plaster …

– Execute 80% piperack system

+) Expanded EMS House:

– Completion of 70% of the structure: 3rd floor is 50%, 4th floor is 30%

Some photos of the site