As of July 1, 19, the project: PCC1 Thanh Xuan - 44 Trieu Khuc, Thanh Xuan, Hanoi achieved progress as requested by the Owner.

Specifically:

1. Sample apartment: Completed 2 units of interior, are deploying 3 remaining apartments.

2. Complete rough construction:

+ Build to the 14th floor;

+ Placement to the 6th floor;

+ Electrical engineering, fire protection are being deployed to the 9th floor;

3. Structure part:

Concrete placement of Prestressing slab beams to 19th floor.