To 12/10/2018 project: Bach Viet Apartment Complex Areca Garden – Bac Giang progress as requested by the Owner.
Specifically:
Completed the sample floor and sample apartment (4th floor)
- Progress of rough body: Constructed curved 18/22 floors. Expected November 10, 18 construction of roof floor on the 22nd floor. (10 days ahead of schedule).
- Progress of construction: Built to the 15th floor (Achieving progress)
- Progress of external plastering: Finished plastering T1-T11 (Exceeding the schedule of 15 days)
- Progress of plastering: Already warranted to 8th floor (Reach)
- Progress of tiling: Has been constructed to the 7th floor (Dat)
- M&E progress: Has been constructed to the 11th floor (Dat)
- Pccc progress: Already constructed to level 6 (Dat)