By July 23, 2019, the project: MEIKO Electronics Vietnam Factory Phase 3 reached the progress as required by the Owner.
Specifically:
+) Factory No. 3:
- Complete 100% of the structure
- Completing 98% of finished parts: installing clean room panel; erection of purlins, wall construction, installation of structural steel for the 1st floor equipment, chiller pipe support, installation of fire-fighting water supply pipes, air-conditioning pipes, sanitary equipment, tiled floor 4 and toilet born …
- Perfecting the 2nd and 3rd floors with 90% of the extra parts: installing panel, installing gypsum ceiling ...
+) Extended ESD house:
- Complete 100% of the structure
- Completion of 99% of finished parts: construction of walls, plastering, painting inside and outside the house, epoxy coating on floors ...
- Construction of 100% piperack system
+) EMS house:
- Complete 100% of the structure
- Completing 98% of the finishing part: building walls, plastering, painting inside and outside the house, installing clean room panel, erecting wall purlins, correcting walls, installing water supply systems, sanitary tiles ...