On April 7, 2021, the Park Kiara - Park city luxury apartment project phase 3B has achieved the following progress: :
1. Complete the entire underground structure.
2. Construction of body structure:
- Pillars on floor 12B, tower A.
- Floor beams 12A, Tower B.
3. MEP work:
- Floor sound pipe system from A to T12B, tower B to T12A.
- Complete:
+ Tower A to 5th floor, drainage shaft to T7.
+ Tower B completes the drainage axis to T6.
4. Plastering work:
- Tower A:
+ Construction: T8 – 30%; T7 - 70%; T6 – 90%; T5 - 95%.
+ Inner plaster: T5 - 25%.
- Tower B:
+ Construction: T5 - 85%
5. Covering works: 90%